Project Planning Diagrams

Faz-1 Sprint Roadmap ve Epic Dependency Graph - Legends DXP Platform

Sprint Roadmap - Golden Circle (v2)

10 Subat 2026 - 11 Mayis 2026 | 6 Sprint + Buffer Week | Icten Disa Onceliklendirme

Toplam Sprint
6
Circle
3
Toplam Task
~65
Toplam SP
~337
gantt title Golden Circle Sprint Roadmap (10 Sub - 11 May 2026) dateFormat YYYY-MM-DD axisFormat %d %b section INNER - Sprint A Admin Core + Auth :sa-core, 2026-02-10, 14d Siparis Yonetimi :sa-order, 2026-02-10, 14d Urun Listesi :sa-prod, 2026-02-10, 14d section INNER - Sprint B Tema Park Urun CRUD :sb-crud, 2026-02-24, 14d Kullanici Yonetimi :sb-user, 2026-02-24, 14d section MIDDLE - Sprint C CMS Icerik Yonetimi :sc-cms, 2026-03-10, 14d Medya Kutuphanesi :sc-media, 2026-03-10, 14d section MIDDLE - Sprint D Kampanya/Kupon :sd-camp, 2026-03-24, 14d Raporlama Baslangici :sd-report, 2026-03-24, 14d section OUTER - Sprint E Satis Sonrasi Islemler :se-ops, 2026-04-07, 14d Store Admin (Lite) :se-store, 2026-04-07, 14d section OUTER - Sprint F Store Public + Checkout :sf-store, 2026-04-21, 14d Security + Polish :sf-sec, 2026-04-21, 14d section Buffer Buffer Week :buff, 2026-05-05, 7d section Milestones M1 - Admin Panel Core :milestone, m1, 2026-02-23, 0d M2 - Urun CRUD Complete :milestone, m2, 2026-03-09, 0d M3 - CMS Live :milestone, m3, 2026-03-23, 0d M4 - Campaign Ready :milestone, m4, 2026-04-06, 0d M5 - Operations Complete :milestone, m5, 2026-04-20, 0d M6 - Production Launch :milestone, m6, 2026-05-11, 0d
INNER - Sprint A: Admin + Siparis
INNER - Sprint B: Urun CRUD + Kullanici
MIDDLE - Sprint C: CMS
MIDDLE - Sprint D: Kampanya + Raporlama
OUTER - Sprint E: Operasyonlar + Store
OUTER - Sprint F: Security + Polish
Milestone
Sprint Circle Tarih Odak SP Milestone
A INNER 10-23 Sub Admin Core + Siparis + Urun Listesi ~52 M1 Admin Panel Core
B INNER 24 Sub - 9 Mar Tema Park Urun CRUD + Kullanici Yonetimi ~55 M2 Urun CRUD Complete
C MIDDLE 10-23 Mar CMS (Icerik Yonetimi) ~49 M3 CMS Live
D MIDDLE 24 Mar - 6 Nis Kampanya/Kupon + Raporlama ~46 M4 Campaign Ready
E OUTER 7-20 Nis Satis Sonrasi Operasyonlar + Store Lite ~54 M5 Operations Complete
F OUTER 21 Nis - 4 May Store Public + Security + Polish ~52 M6 Production Launch

Epic Dependency Graph

Golden Circle - Icten disa bagimlilik akisi (6 Sprint, ~65 Task)

flowchart TB subgraph SA[Sprint A - INNER: Admin Core] LAYOUT[Admin Layout + Nav ~5 SP] AUTH[Admin Auth ~5 SP] API[API Client ~3 SP] ORDER[Siparis Listesi + Detay ~10 SP] PRODLIST[Urun Listesi ~5 SP] PAYMENT[Odeme Izleme ~5 SP] DASH_A[Dashboard Widgets ~3 SP] end subgraph SB[Sprint B - INNER: Urun CRUD + Kullanici] PRODFORM[Urun Olusturma Formu ~5 SP] TICKET[Bilet Detay/Duzenleme ~5 SP] EVENT[Etkinlik/Deneyim ~5 SP] FOOD[Yemek Urunu ~5 SP] ADDON[Eklenti Urunu ~3 SP] PRICE[Fiyat/Kapasite ~3 SP] USERLIST[Kullanici Listesi ~5 SP] USERFORM[Kullanici Formu ~5 SP] PERM[Yetki Matrisi ~3 SP] end subgraph SC[Sprint C - MIDDLE: CMS] MEDIA[Medya Kutuphanesi ~5 SP] CONTENT[Icerik Editoru ~8 SP] PAGES[Sayfa Yonetimi ~5 SP] MENU[Menu Yonetimi ~5 SP] CALENDAR[Etkinlik Takvimi ~5 SP] end subgraph SD[Sprint D - MIDDLE: Kampanya + Rapor] CAMPLIST[Kampanya Listesi ~5 SP] CAMPFORM[Kampanya CRUD ~5 SP] COUPON[Kupon Yonetimi ~5 SP] REPORT1[Satis Raporlari ~5 SP] REPORT2[Gelir Analizi ~5 SP] end subgraph SE[Sprint E - OUTER: Satis Sonrasi + Store] CHECKIN[Check-in QR ~8 SP] CANCEL[Iptal/Iade ~5 SP] TRANSFER[Rezervasyon Transfer ~5 SP] STORECAT[Store Urun Katalogu ~5 SP] STOREINV[Envanter Yonetimi ~5 SP] end subgraph SF[Sprint F - OUTER: Store Public + Polish] RATELIM[Rate Limiting ~3 SP] STOREPUB[Store Public Site ~5 SP] STORECHK[Store Checkout ~8 SP] AUDIT[Audit Log ~5 SP] E2E[E2E Test Suite ~8 SP] end LAYOUT --> ORDER LAYOUT --> PRODLIST API --> AUTH API --> ORDER API --> PRODLIST API --> PAYMENT ORDER --> DASH_A PRODLIST --> PRODFORM PRODFORM --> TICKET PRODFORM --> EVENT PRODFORM --> FOOD PRODFORM --> ADDON TICKET --> PRICE LAYOUT --> USERLIST USERLIST --> USERFORM USERFORM --> PERM MEDIA --> CONTENT CONTENT --> PAGES PAGES --> MENU CONTENT --> CALENDAR CAMPLIST --> CAMPFORM CAMPFORM --> COUPON ORDER --> REPORT1 REPORT1 --> REPORT2 ORDER --> CHECKIN ORDER --> CANCEL ORDER --> TRANSFER LAYOUT --> STORECAT STORECAT --> STOREINV STORECAT --> STOREPUB STOREPUB --> STORECHK LAYOUT --> AUDIT E2E -.-> STORECHK classDef sa fill:#166534,stroke:#22c55e,color:#fff classDef sb fill:#1e40af,stroke:#3b82f6,color:#fff classDef sc fill:#7c2d12,stroke:#f97316,color:#fff classDef sd fill:#6b21a8,stroke:#a855f7,color:#fff classDef se fill:#0e7490,stroke:#06b6d4,color:#fff classDef sf fill:#b91c1c,stroke:#ef4444,color:#fff class LAYOUT,AUTH,API,ORDER,PRODLIST,PAYMENT,DASH_A sa class PRODFORM,TICKET,EVENT,FOOD,ADDON,PRICE,USERLIST,USERFORM,PERM sb class MEDIA,CONTENT,PAGES,MENU,CALENDAR sc class CAMPLIST,CAMPFORM,COUPON,REPORT1,REPORT2 sd class CHECKIN,CANCEL,TRANSFER,STORECAT,STOREINV se class RATELIM,STOREPUB,STORECHK,AUDIT,E2E sf
Sprint A - INNER: Admin Core
Sprint B - INNER: Urun CRUD
Sprint C - MIDDLE: CMS
Sprint D - MIDDLE: Kampanya
Sprint E - OUTER: Satis Sonrasi
Sprint F - OUTER: Store + Polish

Milestone Timeline

6 Major Milestone - Golden Circle Teslim Noktalari (Subat - Mayis 2026)

timeline title Golden Circle Milestones section Subat 2026 M1 (23 Sub) : Admin Panel Operasyonel : Siparis + Odeme + Urun Listesi M2 (9 Mar) : Urun Yonetimi Tam : Tum Tema Park Urunu CRUD + Kullanici Yonetimi section Mart 2026 M3 (23 Mar) : CMS Hazir : Icerik Editoru, Sayfa, Menu, Takvim M4 (6 Nis) : Kampanya + Rapor Hazir : Kampanya/Kupon + Satis Raporlari section Nisan 2026 M5 (20 Nis) : Operasyonlar Tam : Check-in, Iptal/Iade, Store Admin section Mayis 2026 M6 (4 May) : Production Ready : Store Public, Security, E2E, Polish
Milestone Tarih Deliverables Success Criteria
M1 23 Subat 2026 Admin Panel Operasyonel Admin login, siparis listesi/detay, odeme izleme, urun katalogu goruntulenebilir
M2 9 Mart 2026 Urun Yonetimi Tam Tum tema park urun tipleri (bilet, etkinlik, deneyim, eklenti, yemek) CRUD calisiyor, kullanici/yetki atama aktif
M3 23 Mart 2026 CMS Hazir Icerik editoru, sayfa CRUD, menu yonetimi, etkinlik takvimi, medya kutuphanesi calisiyor
M4 6 Nisan 2026 Kampanya + Rapor Hazir Kampanya olusturma, kupon sistemi, satis/gelir raporlari calisiyor
M5 20 Nisan 2026 Operasyonlar Tam QR check-in, iptal/iade, transfer, Store admin urun/envanter yonetimi calisiyor
M6 4 Mayis 2026 Production Ready Store public site, rate limiting, audit log, E2E testler, UAT tamamlanmis

Team Allocation per Sprint

Golden Circle - Takim bazli sprint dagilimi (Backend API hazir, oncelik Frontend)

pie showData title Sprint B Team Allocation (Highest Load) "Frontend" : 50 "Design" : 8 "Backend" : 5 "QA" : 10
Team A B C D E F
Frontend Critical Critical Critical High High High
Design High High High High Med Low
Backend Low Low Low Low High Med
QA Med Med Med High High Critical
Critical - Peak workload, blockers possible
High - Full capacity
Medium - Normal load
Low - Support/review focus